Unlocking Africa’s digital infrastructure future, are data centre developments the key?

By Conrad Purcell, partner, and Kayley Rousell, associate, in the Energy, Power and Natural Resources Practice Group in the London office of Haynes Boone.

Investment in the African data centre market is projected to reach $5 billion by 2026, reflecting a compound annual growth rate of approximately 15% during the 2021 – 2026 period . This expansion is driven by a number of factors including, growth in internet penetration and mobile data usage, population growth and urbanisation and demand for digital services such as artificial intelligence (“AI”) and cloud computing. From a project finance perspective, data centre development in sub-Saharan Africa presents a dynamic mix of opportunities and challenges, shaped by sustainability demands, infrastructure gaps and evolving policy landscapes. This article will explore the opportunities and challenges of data centre development via project finance in sub-Saharan Africa, in particular unpacking the typical structure used, potential regional challenges and the types of data centre projects evolving across the continent. 

Project Finance Structures in Africa

For data centre developments in sub-Saharan Africa being financed by way of project finance, it is often the case that debt from commercial banks cannot be readily obtained, particularly in countries with limitations on liquidity in their banking markets or where there are considerable local political or market risks. To bridge this gap, financing in sub-Saharan Africa is often facilitated by multilateral or bilateral development banks known as development finance institutions (“DFIs”). DFIs are specialised finance institutions that provide long term financing to facilitate economic, environmental and social development and are integral to the success of projects across the continent of Africa. DFIs however are not banks and therefore do not have internal functions to provide certain services, and as such a project finance structure involving DFI lending will also require roles such as a facility agent, a security trustee or agent and an account bank to be fulfilled by other entities such as local or international banks. From a deal structure perspective a project financing for a data centre can largely be split into three core areas: (i) the finance documents (such as the main facility agreement or common terms agreement, security documents and intercreditor deed); (ii) project documents (such as leases, engineering, procurement and construction contracts (“EPC”) and operation and management contracts (“O&M”) and; (iii) a shareholders agreement (governing the equity side of the project). In sub-Saharan Africa in particular, the number and type of potential external risk factors (as discussed in more detail below) are specific to each African jurisdiction, but in order to mitigate such risks, this is often dealt with by a comprehensive package of representations and warranties included within the finance documents. 

Navigating African Regional Realities

Due to its size, rapid population growth and government prioritisation of expansion of digital infrastructure, Africa offers strong potential for continued data centre development. However, there are a number of regional challenges which must be considered before commencing a data centre project on the continent. 

African data centres face significant power usage effectiveness (“PUE”) challenges (PUE being how efficiently a data centre uses energy) primarily due to a warm climate and unstable national power grids. These grids frequently experience rolling blackouts meaning that reliance is placed on expensive, fossil-fuel dependent backup generators posing notable environmental challenges for projects of this kind. However, whilst such legacy power grid issues continue to exist, countries such as Ivory Coast and Senegal are actively investing in renewables such as wind and solar with a view to stabilising historic issues with power source reliability.

Other challenges for data centre development in Africa may include a shortage in availability of experienced contractors within the market and particularly those contractors who have the resources to underwrite the liabilities associated with contracting to build large scale data centre projects. In addition, developers may face civil unrest and other political challenges which can result in project delays and increased costs. 

Collocation vs Hyperscale

Data centre development in Africa for the most part can be split into five main hubs being: South Africa (408 MW of capacity), Nigeria and Egypt (140 MW and 118 MW of capacity respectively), Kenya (79 MW of capacity) and Morocco (65 MW of capacity) , however data centre projects have also expanded into countries such as Ethiopia, Uganda and Ivory Coast as the demand for digital infrastructure continues to increase. Data centre developments can largely be split into two categories: (i) collocated data centres which are typically owned and operated by third-party providers and are facilities which have multiple tenants which rent space, power and cooling infrastructure; and (ii) hyperscale data centres which are large scale facilities owned and operated by large cloud providers (including AI) such as Microsoft Azure, Amazon Web Services, Google Cloud and Oracle Cloud. In Africa, hyperscale data centre development has generally been slow, with only Kenya, Egypt, Nigeria and South Africa having a presence of hyperscale projects and South Africa being the only cloud region in Africa containing all cloud operators that are in the continent. Contrasting this with OECD countries wherein hyperscale data centre developments are commonplace, the reliance on predominantly collocated developments for sub-Saharan African countries can be challenging. Collocated data centre developments are highly reliant on anchor tenants (such as telcos and banks) and in their absence long-term collocation contracts and leases are essential for ensuring predictable cash flows. As a result of this higher merchant risk, from a project finance perspective such risk is likely to be reflected in both the nature of the negotiations and the terms of the finance documents such as more stringent ratios or a higher margin. Despite this, collocated data centre projects are generally smaller in size and less capital intensive than hyperscale projects, with the typical build cost of a Tier III data centre facility being between $5 - $15 million making them suitable for local investors and ultimately quicker to deploy to market. 

Data centre development in sub-Saharan Africa is accelerating, driven by rising digital demand and infrastructure investment. While project finance through DFI lending offers a viable route for funding these projects, they still come with challenges such as power grid reliability, political and social instability and contractor limitations. Despite these hurdles, strategic risk mitigation, market appropriate contract drafting and surging demand for digital services are driving momentum. In addition, whilst collocated data centres remain dominant over hyperscale projects throughout sub-Saharan Africa (namely due to their lower capital requirements), there appears to be, slow but steady, expansion from hyperscale focussed players. As the region evolves, balancing flexibility, sustainability and financial viability of data centre developments will be key to unlocking the full potential of Africa’s digital future. 

By Dave King, Product Engineering Architect at Cadence.
By Straightline Consulting’s Managing Director, Craig Eadie.
By Juan Colina, EMEA Data Centre & IT Segment Leader at Eaton.
By Aashna Puri, Global Strategy and Expansion Director, CyrusOne.
By Matt Powers, vice president of technology & support services, Wesco.
Artificial intelligence (AI) workloads are already transforming data centres, and at speed. From...
By Roland Mestric, Head of Strategic Marketing, Network Infrastructure, Nokia.
By Matthew Whalley, Managing Director, Ilex Content Strategies.